For large loads in ERCOT, few hours of the year matter more than four 15-minute intervals each summer. Your demand during the ERCOT system's peak interval in June, July, August, and September can set the demand you are billed on for the transmission component of your delivery charges for the following 12 billing months. At some TDSPs, transmission-voltage customers' distribution charges are billed on it too. This mechanism is called 4CP (four coincident peak). This page explains how it works, why it rewards curtailment, and how to think about the cost of curtailing versus the cost of missing a peak.
Where 4CP comes from
ERCOT transmission owners recover their costs through wholesale transmission rates approved by the Public Utility Commission of Texas. Under the PUCT's transmission rule, those costs are allocated to each distribution service provider (DSP) by its share of the average ERCOT coincident peak demand for June, July, August, and September. The ERCOT average 4CP is the coincident demand during "the four intervals coincident with ERCOT system peak for the months of June, July, August, and September, divided by four." Each DSP is billed on its previous year's average 4CP (16 TAC §25.192).
ERCOT calculates these figures from settlement data and publishes the Four Coincident Peak calculations for each DSP every year (ERCOT, 4CP Calculations; ERCOT data product NP9-83-M). One technical detail: wholesale storage load is excluded from the 4CP demand used to set and allocate transmission rates (16 TAC §25.192(a), (b)(1), and (d); ERCOT Nodal Protocols §9.17.1). ERCOT has also noted that real-time operational load includes wholesale storage load, so it can differ from the load used to determine the settlement peak (ERCOT Market Notice M-B080124-01).
How it reaches a customer's bill
TDSPs pass transmission costs to retail customers through a transmission cost recovery charge. For larger customers, that charge can be billed on the customer's own 4CP demand. Oncor's tariff for secondary and primary service is one published example:
- A premises that has set an NCP of at least 700 kW in any previous billing month is billed the transmission cost recovery factor on its 4CP kW. Customers already billed on 4CP kW before the tariff took effect stay on it (Oncor Tariff for Retail Delivery Service, Sheets 1.3, 1.5, 1.6).
- 4CP kW is "the average of the Retail Customer's integrated 15-minute demands at the time of the monthly ERCOT system 15-minute peak demand for the months of June, July, August and September of the previous calendar year" (same source).
- For these classes, it is updated each January 1 and "remain[s] fixed throughout the calendar year." Secondary and primary customers with no 4CP history are billed on their NCP kW instead (same source; see also Oncor, Delivery Charges 101).
Transmission-voltage service works differently. At Oncor, AEP Texas, CenterPoint, and TNMP, transmission-voltage customers are always billed transmission cost on 4CP, with no 700 kW threshold. A new transmission-voltage customer without 4CP history is billed on an estimated 4CP, not on its monthly peak. The estimate is the average of its actual coincident peaks if it has at least two that are representative, or otherwise its monthly peak × the class's transmission coincidence factor. At Oncor, AEP Texas, and TNMP, if a new customer's actual coincident peaks aren't representative, the estimate can instead be set by mutual agreement. The "January 1 … fixed throughout the calendar year" wording above comes from the secondary and primary schedules and does not appear in Oncor's or TNMP's transmission schedules. CenterPoint and TNMP bill this class in 4CP kVA, not kW, so power factor is built into the billing determinant (Oncor Tariff, Sheet 1.7; AEP Texas Tariff, §6.1.1.1.5; CenterPoint Tariff, Sheet 6.5; TNMP Tariff, §6.1.1.1.6).
Thresholds (some set in kW, some in kVA), billing units, reset dates, and the treatment of new customers all vary by TDSP and rate class. CenterPoint, for example, uses a 700 kVA threshold for secondary and primary service, applied regardless of meter type, and updates 4CP with the February billing month rather than January 1. A CenterPoint secondary or primary customer with no 4CP history is billed on its monthly peak kVA at a separate NCP rate (CenterPoint Tariff, Sheets 6.3–6.4 and Rider TCRF, Sheet 6.13). Always check your own TDSP's tariff.
The key point: what your site draws during four specific 15-minute intervals sets the demand you are billed on, every month, for the following 12 billing months. That billed 4CP demand is fixed for the year, but the $/kW (or $/kVA) rate is not. TDSPs update their transmission cost recovery riders during the year, typically on March 1 and September 1 at Oncor, AEP Texas, and TNMP (Oncor Tariff, Rider TCRF, Sheet 6.1; AEP Texas Tariff, Rider TCRF; TNMP Tariff, Rider TCRF, §6.1.1.6.1). The charge scales roughly linearly with your load in those intervals. On tariffs with a power-factor adjustment, such as Oncor's and AEP Texas's (below 95% lagging), each coincident peak can also be scaled up for low power factor (Oncor Tariff, §5.5.5; AEP Texas Tariff, §5.5.5).
Predicting the peaks
The official 4CP intervals are determined from settlement data, not designated before they occur. Under 16 TAC §25.192(d) and ERCOT Nodal Protocols §9.17.1, ERCOT must calculate each year's average 4CP from the most recent aggregate settlement data and file it with the Commission by December 1, for use in the following year's transmission billing. During the summer, market participants who want to watch for potential peak intervals do so in near real-time, including by adjusting operational load for wholesale storage load (ERCOT Market Notice M-B080124-01). Some patterns help:
- One peak per month, June through September. A peak caught in June can't be undone, but each later month is a fresh interval.
- Late afternoon on hot weekdays. Hashrate Index reports that the 2025 peaks all fell between 16:00 and 18:00 Central Time (Hashrate Index). Past timing is a guide, not a rule.
- Inputs: ERCOT's published load forecasts and real-time system load, weather forecasts, the running monthly maximum, and the day of the week.
Since the exact interval is uncertain, operators usually curtail on several candidate days each month, during a window of an hour or more around the likely peak, instead of trying to hit a single interval. That tradeoff drives the economics.
Curtailment, conceptually
A flexible load such as a Bitcoin miner, some HPC workloads, or interruptible industrial processes can lower its 4CP by reducing its draw during likely peak windows. What matters is your integrated 15-minute demand during the actual peak interval, so the load has to be down for that whole interval. Ramp-down and ramp-up times count. A site that is still ramping down at the start of the interval gets credit only for what it actually avoided.
Curtailment has costs: lost production or revenue, wear from cycling, and staff time. Some supply contracts include minimum-volume, bandwidth, or curtailment provisions that can trigger charges when you reduce load. Review those terms before you plan.
The curtail-vs-miss math (illustrative)
Every number in this example is illustrative. It is not a tariff rate, a forecast, or a quote.
Assumptions:
- A flat 10 MW (10,000 kW) flexible load.
- An illustrative transmission charge of $5.00 per 4CP kW per month. Actual rates vary by TDSP and rate class: as of November 2026, most 4CP rates we reviewed in the current transmission cost recovery riders of Oncor, AEP Texas, CenterPoint, and TNMP were above $5.00 per 4CP kW or kVA per month, but not all (TNMP's Primary rates, for example, were lower) (Oncor Tariff, Rider TCRF, Sheet 6.1; AEP Texas Tariff, Rider TCRF; CenterPoint Tariff, Rider TCRF, Sheet 6.13; TNMP Tariff, Rider TCRF, §6.1.1.6.1). Check your TDSP's current rider.
- An illustrative net margin lost while curtailed of $30 per MWh (revenue forgone minus energy cost avoided).
- The site curtails fully during each curtailment window.
- Units are kW. Where 4CP is billed in kVA, divide the kW by power factor first (at 0.95, 10,000 kW ≈ 10,526 kVA).
Cost of riding through all four peaks
- 4CP = (10,000 + 10,000 + 10,000 + 10,000) ÷ 4 = 10,000 kW
- Annual charge = 10,000 kW × $5.00 × 12 months = $600,000
Value of each peak
- Each peak interval at full load adds 10,000 ÷ 4 = 2,500 kW to the average.
- 2,500 kW × $5.00 × 12 = $150,000 per peak per year
Cost of curtailing on candidate days
- One 2-hour window at 10 MW = 20 MWh × $30 = $600 per event
- Say 8 candidate days a month for 4 months = 32 events × $600 = $19,200 per summer
Outcomes
| Scenario | 4CP kW | Next-year transmission charge | Curtailment cost | Total |
|---|---|---|---|---|
| No curtailment | 10,000 | $600,000 | $0 | $600,000 |
| Catch all 4 peaks | 0 | $0 | $19,200 | $19,200 |
| Catch 3, miss 1 | 2,500 | $150,000 | $19,200 | $169,200 |
| Curtail to 1 MW floor, catch all 4 | 1,000 | $60,000 | 32 × 2 h × 9 MW × $30 = $17,280 | $77,280 |
Break-even logic. In this example, one missed peak costs $150,000. Curtailing costs 10 MW × $30 = $300 per hour, so the site could curtail up to $150,000 ÷ $300 = 500 hours in a month before it cost more than missing that month's peak. Real numbers will be much closer than this when margins are high or transmission rates are lower, so run the calculation with your own figures. As a cross-check on scale, Hashrate Index estimates 4CP exposure of "up to ~$50,000 per MW per year" for a site at full load through every peak (Hashrate Index). Our illustrative $5.00/kW-month works out to $60,000 per MW per year, the same order of magnitude.
What the math shows:
- Missing one peak costs a quarter of the full exposure. Curtailment programs therefore lean toward curtailing on more candidate days, not fewer.
- The margin you give up matters. The higher your net margin per MWh, the more each false alarm costs, and the more forecasting accuracy is worth.
- Partial curtailment still pays proportionally. Every kW off during the peak interval comes off the 4CP average.
How Kyber helps
Kyber is a PUCT-registered electricity broker. We can help you estimate your 4CP exposure under your TDSP's current tariff, build a curtail-vs-miss model with your own margins and ramp times, and flag supply-contract terms, such as minimum-volume, bandwidth, or curtailment provisions, that could conflict with a curtailment strategy. Peak forecasting is uncertain, and outcomes depend on your operations and the market. Results aren't assured, and we'll show you the assumptions behind every number.
What this page is not
This page is for general information. It is not a quote, an offer, or a commitment to transact, and it is not a substitute for a signed client agreement.
Sources
All accessed 15 November 2026.
- PUCT, 16 Tex. Admin. Code §25.192, Transmission Service Rates: https://www.puc.texas.gov/agency/rulesnlaws/subrules/electric/25.192/25.192.pdf
- ERCOT, Four Coincident Peak Calculations: https://www.ercot.com/mktinfo/data_agg/4cp
- ERCOT, Data Product Details, NP9-83-M "ERCOT Four Coincident Peak Calculations": https://www.ercot.com/mp/data-products/data-product-details?id=NP9-83-M
- ERCOT, Market Notice M-B080124-01, "4-CP Peak Determination" (Aug. 1, 2024): https://www.ercot.com/services/comm/mkt_notices/M-B080124-01
- Oncor, Tariff for Retail Delivery Service, §§6.1.1.1.3, 6.1.1.1.5–6.1.1.1.7, Sheets 1.3, 1.5–1.7 (Determination of Billing Demand for Rider TCRF; Determination of 4CP kW; eff. June 1, 2026); §5.5.5 (power factor); Rider TCRF §6.1.1.6.1, Sheet 6.1 (rate eff. Oct. 4, 2026): https://www.oncor.com/content/dam/oncorwww/documents/about-us/regulatory/tariff-and-rate-schedules/Tariff%20for%20Retail%20Delivery%20Service.pdf
- Oncor, "Delivery Charges 101": https://www.oncor.com/content/oncorwww/us/en/home/about-us/regulatory/delivery-charges-101.html
- ERCOT, Current Protocols — Nodal, Section 9.17.1, Billing Determinant Data Elements (4-CP calculated from the most recent aggregate Settlement-system data; coincidental MW peak excludes Wholesale Storage Load), https://www.ercot.com/mktrules/nprotocols/current/ (PDF convenience copy of the October 29, 2026 protocols: https://www.ercot.com/files/docs/2026/10/26/October-29-2026-Nodal-Protocols.pdf)
- Public Utility Commission of Texas, Project 58000, Rulemaking to Update Wholesale and IOU Retail Transmission Cost Recovery in the ERCOT Region, https://interchange.puc.texas.gov/search/filings/?ControlNumber=58000
- Senate Bill 6, enrolled text (89th Legislature), Section 6, https://capitol.texas.gov/tlodocs/89R/billtext/html/SB00006F.htm
- Hashrate Index (Luxor), "4CP for Bitcoin Miners: How One Hour Sets a Year of ERCOT Transmission Costs," May 21, 2026: https://hashrateindex.com/blog/4cp-for-bitcoin-miners-how-one-hour-sets-a-year-of-ercot-transmission-costs/
- AEP Texas, Tariff for Retail Delivery Service (book eff. Nov. 6, 2026), §§6.1.1.1.3–6.1.1.1.5 (pp. 121, 124, 129–130); §5.5.5 (pp. 97–98); Rider TCRF (pp. 164–166, eff. Sept. 29, 2026): https://www.aeptexas.com/lib/docs/ratesandtariffs/Texas/AEP_TEXAS_TARIFF_Eff_Nov_6-2026-TC3.pdf
- CenterPoint Energy Houston Electric, Tariff for Retail Delivery Service (file dated Nov. 9, 2026), §§6.1.1.1.3–6.1.1.1.5, Sheets 6.3–6.5; Rider TCRF §6.1.1.6.3, Sheet 6.13 (eff. Sept. 1, 2026): https://assets.centerpointenergy.com/api/public/content/houston-electric-tariff-for-retail-delivery-service.pdf
- Texas-New Mexico Power (TNMP), Tariff for Retail Delivery Service (Docket 58964 book), §§6.1.1.1.3–6.1.1.1.6 (pp. 96–107, eff. Sept. 13, 2026); Rider TCRF §6.1.1.6.1 (pp. 122–125, eff. Sept. 1, 2026): https://tnmp.com/sites/default/files/inline-images/TNMP%20Retail%20Tariff%20%2858964%29.pdf
All rates, margins, and dollar amounts on this page are illustrative and are not TDSP tariff rates or forecasts.
Prices shown are recent or historical ERCOT market data, which may be delayed, and are for information only. They are not a quote, offer, or forecast, and Holocron Kyber does not guarantee any price or savings. Actual costs depend on market conditions, your load, and the terms of your supply contract.