In the ERCOT region, Texas law and a PUCT rule use a 75 megawatt (MW) demand threshold to decide when a new or expanded interconnection is treated as a "large load" and must meet special interconnection standards. This page explains that threshold as it stands in the adopted rule. It is for general information. It is not a quote, an offer, or a commitment to transact, and it is not a substitute for a signed client agreement.
The rule is 16 TAC §25.194, Large Load Interconnection Standards, adopted in PUCT Project 58481. It implements Public Utility Regulatory Act (PURA) §37.0561, which was added by Senate Bill 6 in the 89th Legislature. The official rule text is effective 8 October 2026. Always confirm the current text; the Commission can amend the rule, and related forms and companion rules may still be in progress.
What the statute requires the Commission to do
PURA §37.0561(b) directs the Commission to establish, by rule, standards for interconnecting large-load customers in the ERCOT power region in a manner designed to support business development in this state while minimizing the potential for stranded infrastructure costs and maintaining system reliability.
Section 37.0561(c) says those standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold set by the Commission. The statute tells the Commission to establish a demand threshold of 75 MW unless the Commission determines that a lower threshold is necessary to accomplish the purposes in subsection (b). As of this page's date, the adopted rule uses the 75 MW threshold.
The statute also addresses disclosures, site control, study fees, and financial commitments, and it provides that the Commission may not limit the authority of a municipally owned utility or an electric cooperative to impose additional electric-service requirements for large-load customers on their systems. Those statutory requirements are implemented, in part, by §25.194. This page summarizes the adopted rule. It is not a complete restatement of either the statute or the rule.
Who §25.194 applies to
Under 16 TAC §25.194(b), the section applies to a large load customer that has not energized as of the effective date of the section and that seeks:
- a new interconnection at a single site that is equal to or exceeds 75 MW;
- an expanded interconnection at a single site that equals or exceeds 75 MW for the first time;
- an expanded interconnection at a single site that exceeds 75 MW and is expanding by 75 MW or more; or
- to co-locate with a generation resource.
For an expanded interconnection, the section applies to the incremental load addition. The rule's definition of "large load customer" is an entity requesting a new or expanded interconnection where the customer's total expected non-coincident peak demand at a single site is equal to or exceeds 75 MW, whether at transmission voltage or distribution voltage.
The rule applies to electric utilities, municipally owned utilities, and electric cooperatives interconnecting a large-load customer to the ERCOT system. It does not limit the authority of a municipally owned utility or an electric cooperative to impose additional electric-service requirements on their systems.
Whether a particular project has "energized" as of the effective date, and how a "single site" is determined, are fact-specific questions. This page does not classify any project.
What the adopted rule requires, in outline
The adopted rule is detailed. The outline below is only a map of the main steps. The official text controls.
Before the interconnection request is included in an ERCOT interconnection study, the large-load customer must execute and fund an intermediate agreement with the interconnecting distribution service provider and, if different, the interconnecting transmission service provider. Under §25.194(d), that intermediate agreement must, among other things, include required disclosures — including a demonstration of site control through a legally binding property interest that meets the rule's tests, and a disclosure of whether the customer or certain related parties is pursuing a substantially similar interconnection request in Texas — and it must include a study fee and financial security.
As of the 8 October 2026 official text:
- the study fee is $100,000, due no later than the date the intermediate agreement is executed, with unused amounts returned under the rule;
- intermediate financial security is $50,000 per MW of the requested peak demand for new interconnection requests, or $50,000 per MW of the incremental increase in the peak demand for expanded interconnection requests, posted with the interconnecting utility on the timeline and in a form the rule allows.
After study and as the project moves toward interconnection, the rule requires the customer to execute a standard large-load interconnection agreement (SLLIA), update disclosures, post financial security, and pay contribution in aid of construction (CIAC) for direct interconnection costs. The rule defines a SLLIA as a Commission-approved pro forma agreement executed by the large-load customer, the interconnecting DSP, and, if different, the interconnecting TSP, that at a minimum complies with §25.194. At SLLIA execution, financial security is, under the adopted text, the greater of $50,000 per MW of the contracted peak demand or the costs allocated to the large load customer for system upgrades as a result of a batch zero interconnection study or an interconnection study, with credit or return of security already posted under the intermediate agreement where the rule allows it.
The rule also addresses withdrawal or reduction of requested demand, consequences of inaccurate information, and the return or forfeiture of financial security. Those provisions should be read in the official text. This page does not attempt to restate every condition.
None of these steps is a guarantee of interconnection, of available capacity, or of a date when a site will be energized. Study outcomes, utility work, and ERCOT processes are outside a customer's or a broker's control.
The standard interconnection agreement is still a proposal
The adopted rule assumes a Commission-approved SLLIA. That form has not been adopted as of 15 November 2026.
In Project 59999, Rulemaking to Adopt a Standard Large Load Interconnection Agreement, Commission staff proposed a Standardized Large Load Interconnection Agreement (SLLIA). The Commission's 5 November 2026 request for comments states that the new form is intended to serve as the standard agreement for large loads interconnecting in the ERCOT region, consistent with §25.194, and that it is also intended to integrate transmission-cost-recovery standards for large-load customers that are still pending in Project 58000, including any obligations associated with "minimum billing demand," once those rules are adopted.
The proposed SLLIA is a proposal. Interested persons may file comments in Project 59999 by 14 December 2026. Until the Commission adopts a final form, no one should treat the draft agreement, or any term described in staff's proposal — including any proposed reallocation of capacity after a delay in phased energization — as a final requirement. If this page is updated after adoption, the date-stamp and sources will change.
Project 58000, which would update wholesale and investor-owned-utility retail transmission cost recovery in ERCOT, including 4CP / 12CP allocation and large-load minimum billing, had not been adopted as of this page's date. Those topics are held for a later update and are not explained here.
Loads below 75 MW, including "medium" loads
Section 25.194 is a large-load rule. A load that is below the 75 MW tests in §25.194(b) is not, by that fact, unregulated, but it is not automatically subject to this large-load standard.
The Commission and ERCOT have been gathering information on medium-size interconnection requests — described in ERCOT's 4 November 2026 update in Project 59142 as loads of 10 MW to under 75 MW. That update describes a request for information issued to transmission and distribution service providers on 26 October 2026, with responses due 6 November 2026, covering interconnection requests received from 1 July through 31 October 2026. The RFI was described as being for information purposes.
No medium-load interconnection requirements should be treated as settled. Project 59142 remains a review of interconnection processes. This page does not state what rules, if any, will apply to loads of 10 MW to under 75 MW, and it does not treat informal reports or a survey as a standard.
What this page is not
This page is for general information. It is not a quote, an offer, or a commitment to transact, and it is not a substitute for a signed client agreement. It is not an interconnection study, a determination that a site is a "large load," or a promise of capacity, cost, or timing. It does not interpret implementing rules that have not been adopted.
Sources
Retrieved 15 November 2026.
- Public Utility Commission of Texas, 16 TAC §25.194, Large Load Interconnection Standards, official text effective 8 October 2026 (Project 58481), https://ftp.puc.texas.gov/public/puct-info/agency/rulesnlaws/subrules/electric/25.194/25.194.pdf
- Public Utility Commission of Texas, Order Adopting New 16 TAC §25.194, Project 58481, https://ftp.puc.texas.gov/public/puct-info/agency/rulesnlaws/subrules/electric/25.194/58481adt.pdf
- Texas Utilities Code §37.0561 (PURA), Planning for and Interconnection of Large Loads, https://statutes.capitol.texas.gov/Docs/UT/htm/UT.37.htm
- Public Utility Commission of Texas, Project 59999, Rulemaking to Adopt a Standard Large Load Interconnection Agreement, filings index, https://interchange.puc.texas.gov/Search/Filings?ControlNumber=59999
- Public Utility Commission of Texas, Request for Comments on the Standardized Large Load Interconnection Agreement (SLLIA), Project 59999, Item 4 (5 November 2026), comments due 14 December 2026, https://interchange.puc.texas.gov/Documents/59999_4_1699922.PDF
- Public Utility Commission of Texas, Project 58000, Rulemaking to Update Wholesale and IOU Retail Transmission Cost Recovery in the ERCOT Region, https://interchange.puc.texas.gov/search/filings/?ControlNumber=58000
- Public Utility Commission of Texas, Project 59142, Review of ERCOT's Interconnection Processes for Large Loads, https://interchange.puc.texas.gov/Search/Filings?ControlNumber=59142
- ERCOT, letter and presentations, "ERCOT Updates: Batch Zero Verification and Audit Process, Data Center State and Community Impact RFI, and Medium Load RFI," Project 59142, Item 78 (4 November 2026), https://interchange.puc.texas.gov/Documents/59142_78_1699635.PDF