If you're planning a large load such as a mining block, an HPC hall, or a big industrial line, you will see capacity quoted in two units: MW on the load side and MVA on the transformer nameplate. They aren't interchangeable. Mixing them up is one of the most common ways a capacity plan ends up a few percent short. This page explains the difference, the formulas that connect the two, and why transformers are usually planned well below nameplate.

This page is general education, not engineering advice or an engineering service. Any real installation must be designed and sealed by a Texas-licensed professional engineer where required, and approved by the serving utility.

Real power, apparent power, and power factor

The U.S. Department of Energy compares it to a horse pulling a rail car from beside the track. Only the forward part of the pull moves the car. The sideways part is reactive, non-working effort (DOE, Reducing Power Factor Cost).

The units matter because conductors and transformers heat up with current, and current follows apparent power (kVA or MVA), not MW. A transformer is rated in MVA because its limit is thermal.

The three formulas you need

From the definition of power factor:

PF = P ÷ S → S = P ÷ PF → P = S × PF

For a balanced three-phase system, apparent power and line current are related by:

S = √3 × V(line-to-line) × I → I = S ÷ (√3 × V)

and real power is P = √3 × V × I × PF (ORNL, Power Factor training module). (√3 ≈ 1.732.)

Two consequences follow:

  1. At the same MW, a lower power factor means more MVA and more current. The DOE fact sheet notes that low power factor "reduces your electrical system's distribution capacity by increasing current flow and causing voltage drops" (DOE).
  2. At the same MVA, lower voltage means more current. That is why the same transformer carries thousands of amps on a 480 V secondary but only hundreds on a medium-voltage primary.

Why transformers are usually planned around 80% of nameplate

A transformer's MVA nameplate is a thermal rating under defined conditions. Running near or above it raises winding and oil temperatures, and the paper insulation ages faster at higher temperature. IEEE C57.91, the Guide for Loading Mineral-Oil-Immersed Transformers and Step-Voltage Regulators, covers this. Its scope includes estimating the effects of loading above nameplate, "including damage to insulation, production of gases in oil, and ultimately loss of life," along with the effects of ambient temperature, altitude, and cooling method (IEEE SA, C57.91).

In practice, many designers and owners plan steady loads at about 80% of nameplate. That is a common design margin, not a code or IEEE requirement. The right figure for a given unit depends on its cooling class, ambient temperature, load profile, and the utility's or owner's criteria. Some reasons for the margin:

Worked example: three 3 MVA transformers

Generic, illustrative example. It does not represent any specific site.

A site has three 3 MVA transformers serving a flat load at 0.98 power factor, and the owner plans to 80% of nameplate.

Step 1: Nameplate and planned MVA

Step 2: Convert to real power

So "7.2" on a planning sheet means 7.2 MVA, which is about 7.06 MW of load at 0.98 PF. If the load were 7.2 MW, the transformers would be above the planned limit.

Step 3: Sensitivity to power factor

Step 4: Current

These currents are what feeders, fuses, cutouts, switchgear, and breakers have to be sized for. The upstream path has to carry the planned load too, not just the transformers. Check every element between the utility source and the load.

Practical takeaways

  1. Ask which unit is meant. "5 MW of capacity" and "5 MVA of transformers" are different promises.
  2. Know your power factor. Use measured PF from similar equipment or vendor data, not an assumed 1.0.
  3. Plan on MVA and current, not just MW. Do the conversion at each voltage level.
  4. Treat 80% as a starting point, not a rule. The right loading for a specific unit is an engineering decision based on C57.91-type analysis, ambient, cooling, and load profile.
  5. Check the whole path. Primary protection, conductors, and switchgear can limit capacity before the transformers do.
  6. Check your utility's standard voltages and service limits. They differ by utility. AEP Texas, for example, limits three-phase secondary service to 2,500 kVA unless otherwise agreed, so larger loads there take primary or transmission service (AEP Texas Tariff, §6.2.2).

How Kyber helps

Kyber is a PUCT-registered electricity broker. When you're procuring power for a large load, we can help you get the capacity numbers consistent for procurement purposes, in MW versus MVA, at what power factor and what loading, before they go into supply discussions and contract volumes. Equipment design and loading decisions belong with your licensed engineer and your utility. We don't provide sealed engineering or promise capacity or timelines the utility controls.

What this page is not

This page is for general information. It is not a quote, an offer, or a commitment to transact, and it is not a substitute for a signed client agreement.

Sources

All accessed 15 November 2026.

  1. U.S. EIA, Glossary, "A" (Apparent power): https://www.eia.gov/tools/glossary/index.php?id=A
  2. U.S. EIA, Glossary, "P" (Power factor): https://www.eia.gov/tools/glossary/index.php?id=P
  3. U.S. Department of Energy, Reducing Power Factor Cost (fact sheet): https://www.energy.gov/sites/default/files/2014/04/f15/mc60405.pdf
  4. Oak Ridge National Laboratory, Power Factor (training module; three-phase kW and kVA formulas): https://bptraining.ornl.gov/wp-content/uploads/2021/05/VInPLT-Power-Factor.pdf
  5. IEEE Standards Association, IEEE C57.91, Guide for Loading Mineral-Oil-Immersed Transformers and Step-Voltage Regulators (2011 page, showing the C57.91-2025 successor and scope): https://standards.ieee.org/ieee/C57.91/5297/
  6. EC&M, "NEC: Branch-Circuit Overcurrent Protection" (NEC Art. 100 continuous load; 210.20(A) 125% rule): https://www.ecmweb.com/national-electrical-code/article/20900335/nec-branch-circuit-overcurrent-protection
  7. Schneider Electric, "NEC Information of Note" (text of NEC 210.20(A) and exception): https://www.productinfo.schneider-electric.com/na-std-ref/viewer/5c0fee4b347bdf0001de4d55/5c0fee5b347bdf0001de4d6b/r/NECInformationOfNote-F20BDBCC
  8. EC&M, "Ensuring Accuracy in Demand Factors with the NEC" (125% for continuous loads per 210.19(A)(1), 210.20(A), 215.3): https://www.ecmweb.com/national-electrical-code/article/55269591/ensuring-accuracy-in-demand-factors-with-the-nec
  9. EC&M, "Sizing a Circuit Breaker" (80% = 1 ÷ 1.25; 100%-rated assemblies): https://www.ecmweb.com/basics/article/20898940/sizing-a-circuit-breaker
  10. AEP Texas, Tariff for Retail Delivery Service (book eff. Nov. 6, 2026), §6.2.2 (pp. 316–317; standard voltages, 2,500 kVA three-phase secondary limit); §5.5.5 (pp. 97–98; power factor): https://www.aeptexas.com/lib/docs/ratesandtariffs/Texas/AEP_TEXAS_TARIFF_Eff_Nov_6-2026-TC3.pdf
  11. Oncor, Tariff for Retail Delivery Service, §5.5.5 (power factor; p. 58): https://www.oncor.com/content/dam/oncorwww/documents/about-us/regulatory/tariff-and-rate-schedules/Tariff%20for%20Retail%20Delivery%20Service.pdf
  12. Texas-New Mexico Power (TNMP), Tariff for Retail Delivery Service (Docket 58964 book), §5.5.5 (pp. 78–79; power factor): https://tnmp.com/sites/default/files/inline-images/TNMP%20Retail%20Tariff%20%2858964%29.pdf

Prices shown are recent or historical ERCOT market data, which may be delayed, and are for information only. They are not a quote, offer, or forecast, and Holocron Kyber does not guarantee any price or savings. Actual costs depend on market conditions, your load, and the terms of your supply contract.

Holocron Kyber