Demand Charges Explained: kW vs kWh on a Texas Commercial Bill

As of: (America/Chicago)

Last reviewed:

Insights

Opens in a new tab.

On a Texas commercial bill, two numbers drive delivery cost: how much energy you used and how fast you used it. A site that draws hard for a few minutes can pay more than a site that uses the same energy evenly across the month. This page covers the difference between kW and kWh, how a 15-minute interval becomes "billed demand," and how demand ratchets work in principle.

kW and kWh are different quantities

Oncor uses the same comparison. Its demand register "records the highest amount of electricity used during any given 15-minute interval during the monthly billing cycle (kW)" and resets each cycle (Oncor, Delivery Charges 101).

A demand charge is the part of a bill "based on the consumer's maximum electric capacity usage" under the applicable rate schedule (EIA glossary). The wires, transformers, and substations serving your site have to be sized for your peak, not your average. That is why delivery tariffs charge for demand.

How a 15-minute interval becomes billed demand

The EIA defines a demand interval as the period over which flow is measured, "usually in 15-, 30-, or 60-minute increments" (EIA glossary). In Texas, TDSP tariffs typically use 15 minutes. Oncor's tariff, for example, defines NCP kW (non-coincident peak) as "the kW supplied during the 15-minute period of maximum use during the billing month" (Oncor Tariff for Retail Delivery Service, Sheet 1.3).

Demand is averaged ("integrated") over the interval. It is not an instantaneous spike. To turn interval energy into demand, divide the kWh by the interval length in hours:

Interval demand (kW) = kWh in the interval ÷ 0.25 h = kWh × 4

Illustrative example: A site runs at 120 kW. For 5 minutes of one interval, a large compressor pushes it to 300 kW.

The meter does not record 300 kW, but the short burst still raises that month's peak from 120 kW to 180 kW. If the burst had lasted the whole 15 minutes, demand would have been 300 kW. Short starts get softened by averaging. Sustained overlaps do not.

The highest 15-minute reading in the billing period is your metered peak. Your billed demand can be higher than that, because of a ratchet or a power-factor adjustment (both covered below).

Some TDSPs bill demand in kVA (apparent power) instead of kW. Where they do, it is usually every demand-billed class, not a special case, and class thresholds may also be set in kVA. CenterPoint Houston, for example, bills its demand-metered secondary, primary, and transmission-voltage classes in kVA (CenterPoint Tariff for Retail Delivery Service, Sheets 6.3–6.5). TNMP bills secondary and primary demand in kW, but bills transmission-voltage customers' transmission charges on 4CP kVA (TNMP Tariff, §6.1.1.1.6). When TDU base rates are set for nonresidential secondary-voltage customers, those customers are to be billed on a kWh, kW, or kVA basis (16 TAC §25.244(c)). On kVA billing, power factor directly affects billed demand. Our MVA vs MW page explains why.

Power factor can matter on kW billing too. The Oncor, AEP Texas, and TNMP tariffs allow billed demand to be raised when power factor is below 95% lagging: adjusted kW = actual kW × 0.95 ÷ power factor (Oncor Tariff, §5.5.5; AEP Texas Tariff, §5.5.5; TNMP Tariff, §5.5.5). Illustrative: a 500 kW peak at 0.90 power factor could be billed as 500 × 0.95 ÷ 0.90 ≈ 528 kW.

Ratchets: when last summer's peak sets this winter's bill

A demand ratchet is a tariff provision that bills a customer on the greater of the current month's peak or "some fixed percentage of the peak demand for that customer during previous months" (16 TAC §25.244(b)).

Ratchet terms vary by TDSP and rate class, and some classes have none. Here is one published example. For its secondary, primary, and transmission demand classes, Oncor bills the Distribution System Charge on the higher of the current month's NCP kW or 80% of the highest monthly NCP kW in the preceding 11 months (Oncor Tariff, Sheets 1.3, 1.5–1.7). At secondary voltage, Oncor's tariff does not apply that ratchet to the base Distribution System Charge for loads whose prior-11-month peak was 20 kW or less, or for loads above 20 kW with an annual load factor of 25% or less. Some riders are still billed on ratcheted demand. Primary-voltage service keeps the 20 kW carve-out but has no load-factor carve-out, and transmission-voltage service has neither (Oncor Tariff, Sheet 1.3 and Sheets 1.5–1.7). The 25% carve-out follows a PUCT rule. Where a demand ratchet is used in a TDU's base rates, it must not apply to a nonresidential secondary-voltage customer with an annual load factor of 25% or less (16 TAC §25.244(c)). That rule covers only nonresidential secondary-voltage service through one point of delivery and one meter. Primary- and transmission-voltage customers don't get it.

The other large ERCOT TDSPs draw the lines differently:

Where a ratchet applies, it can set the billing demand for other demand-based riders too, not just the distribution charge. Transmission cost recovery is usually billed on 4CP instead, or on the current month's peak (or an estimated 4CP) until 4CP history exists. See our 4CP page.

Illustrative ratchet example (80% ratchet, illustrative rate of $7.00 per billing kW):

MonthActual NCP kW80% of prior 11-month maxBilling kWDistribution demand charge
July500n/a (sets new max)500500 × $7 = $3,500
January3000.80 × 500 = 400400400 × $7 = $2,800

In January, the site pays for 100 kW it did not use: 100 × $7 = $700 that month. That continues every month until the July peak rolls out of the 11-month window or a new peak replaces it. One unmanaged peak can show up on bills for most of a year.

When a new retail customer takes over an existing premises, the Oncor, AEP Texas, and CenterPoint tariffs reset the demand ratchet rather than carrying over the previous occupant's peaks (Oncor Tariff, §4.3.6; AEP Texas Tariff, §4.3.6; CenterPoint Tariff, §4.3.6).

Worked example: same energy, different bills

Two illustrative sites each use 72,000 kWh in one 30-day billing period (30 × 24 = 720 hours). The rates are illustrative only: $0.060/kWh for energy and $10.00 per kW-month for demand-based delivery charges.

Site A (steady)Site B (peaky)
Energy72,000 kWh72,000 kWh
Average load = kWh ÷ 720 h100 kW100 kW
Peak 15-minute demand100 kW250 kW
Energy cost = kWh × $0.060$4,320$4,320
Demand charges = peak kW × $10$1,000$2,500
Demand charges per kWh = $10 × peak kW ÷ kWh$0.0139$0.0347
Total$5,320$6,820
All-in cost per kWh$5,320 ÷ 72,000 = $0.0739$6,820 ÷ 72,000 = $0.0947

The two sites use the same energy, but Site B's all-in rate is about 28% higher, purely because of when it used power. The ratio of average to peak demand is called load factor. Our load factor page covers it.

Three cautions apply to this math, and to our load factor calculator:

Practical ways to flatten peaks

None of these is certain to cut a bill. Results depend on your tariff, contract, and operations.

  1. Read your interval data first. Find the dates and times your monthly peaks were set. Smart-meter interval data is usually enough to find them.
  2. Stagger large starts. Chillers, compressors, kilns, pumps, and EV chargers that all start together after a shutdown or at shift change often set the month's peak.
  3. Sequence restarts after outages. Bringing load back in stages avoids a recovery spike in one 15-minute window.
  4. Use controls with a demand limit. Building automation or load controllers can shed or delay deferrable loads as the running interval approaches a threshold.
  5. Shift flexible processes. Moving batch work, pre-cooling, or charging away from your own peak can lower NCP.
  6. Watch the ratchet window. Where a ratchet applies, a summer peak can set your floor for months. Avoiding one high interval matters more than trimming average use.
  7. Plan equipment testing. Generator or load-bank tests that add grid load can set a peak. Check your tariff and talk to your TDSP before scheduling one. The Oncor, AEP Texas, CenterPoint, and TNMP tariffs will ignore a company-approved test, scheduled with at least 10 days' notice, for ratchet purposes, but they don't approve tests between noon and 8 PM on weekdays from June through September. All four tariffs note that usage during the test can still be billed (Oncor Tariff, §5.5.6; AEP Texas Tariff, §5.5.6; CenterPoint Tariff, §5.5.6; TNMP Tariff, §5.5.6).
  8. Look at power factor. Where demand is billed in kVA, or where the tariff raises billed kW for power factor below 95% lagging, correcting a low power factor can lower billed demand.

How Kyber helps

Kyber is a PUCT-registered electricity broker. We can review your interval data and bills to find what is setting your billed demand, explain how your TDSP's demand provisions apply to your site, and factor your load shape into supply contract comparisons. Delivery charges are set by your TDSP's tariff, not by a broker. We will tell you plainly what can change and what can't. Any savings depend on your load, your tariff, and market conditions.

What this page is not

This page is for general information. It is not a quote, an offer, or a commitment to transact, and it is not a substitute for a signed client agreement.

Sources

All accessed 15 November 2026.

  1. U.S. EIA, Glossary, "K" (Kilowatt; Kilowatthour): https://www.eia.gov/tools/glossary/index.php?id=K
  2. U.S. EIA, Glossary, "D" (Demand charge; Demand interval): https://www.eia.gov/tools/glossary/index.php?id=D
  3. Oncor, "Delivery Charges 101": https://www.oncor.com/content/oncorwww/us/en/home/about-us/regulatory/delivery-charges-101.html
  4. Oncor, Tariff for Retail Delivery Service, §6.1.1.1.3, Sheet 1.3, and §§6.1.1.1.5–6.1.1.1.7, Sheets 1.5–1.7 (rate schedules eff. June 1, 2026); §4.3.6 (ratchet reset); §5.5.5 (power factor); §5.5.6 (equipment testing): https://www.oncor.com/content/dam/oncorwww/documents/about-us/regulatory/tariff-and-rate-schedules/Tariff%20for%20Retail%20Delivery%20Service.pdf
  5. PUCT, 16 Tex. Admin. Code §25.244, Billing Demand for Certain Utility Customers: https://ftp.puc.texas.gov/public/puct-info/agency/rulesnlaws/subrules/electric/25.244/25.244.pdf
  6. AEP Texas, Tariff for Retail Delivery Service (book eff. Nov. 6, 2026), §§6.1.1.1.3–6.1.1.1.5 (pp. 119–130), §4.3.6 (pp. 43–44), §5.5.5 (pp. 97–98), §5.5.6 (pp. 98–99): https://www.aeptexas.com/lib/docs/ratesandtariffs/Texas/AEP_TEXAS_TARIFF_Eff_Nov_6-2026-TC3.pdf
  7. CenterPoint Energy Houston Electric, Tariff for Retail Delivery Service (file dated Nov. 9, 2026), §6.1.1.1.3–§6.1.1.1.5, Sheets 6.3–6.5 (eff. Feb. 26, 2026 and Sept. 17, 2025); Rider DCRF, Sheets 6.14.10–6.14.11; §4.3.6, Sheet 4.1; §5.5.6, Sheet 5.1: https://assets.centerpointenergy.com/api/public/content/houston-electric-tariff-for-retail-delivery-service.pdf
  8. Texas-New Mexico Power (TNMP), Tariff for Retail Delivery Service (Docket 58964 book; rate schedules eff. Sept. 13, 2026), §§6.1.1.1.3–6.1.1.1.6 (pp. 96–107), §5.5.5 (pp. 78–79), §5.5.6 (p. 79): https://tnmp.com/sites/default/files/inline-images/TNMP%20Retail%20Tariff%20%2858964%29.pdf

All rates and dollar amounts on this page are illustrative and are not TDSP tariff rates.

Prices shown are recent or historical ERCOT market data, which may be delayed, and are for information only. They are not a quote, offer, or forecast, and Holocron Kyber does not guarantee any price or savings. Actual costs depend on market conditions, your load, and the terms of your supply contract.