Two businesses can use the same energy in a month and still pay quite different average prices per kWh. Usually the difference comes down to load factor: how steadily a site uses power compared with its peak. On demand-billed Texas service, load factor is one of the most useful numbers on your bill.

What load factor means

The U.S. Energy Information Administration defines load factor as "the ratio of the average load to peak load during a specified time interval" (EIA glossary). A site with a load factor of 100% draws exactly its peak in every interval, which is a flat line. A site with a load factor of 25% averages only a quarter of its peak.

The formula

Average load is energy divided by hours. So:

Load factor = average kW ÷ peak kW = kWh ÷ (peak kW × hours in the period)

The units cancel (kWh ÷ kW·h), so load factor is a plain ratio, usually written as a percentage. For a monthly bill, "hours" is days in the billing period × 24, and "peak kW" is the metered peak: the highest 15-minute kW reading in that billing period. Your billed demand can be higher than the metered peak because of a demand ratchet or a power-factor adjustment. Use the metered peak for load factor.

If your bill shows demand in kVA, convert to kW first: kW = kVA × power factor. CenterPoint Houston, for example, bills its demand-metered classes in kVA (CenterPoint Tariff, Sheets 1.1 and 6.3–6.5). Using kVA directly makes load factor look lower than it is. Illustrative: at a power factor of 0.90, a true 60% load factor would show as 54%.

Texas TDSP tariffs use the same idea. Oncor, for example, calculates an annual load factor as kWh used in the 12 billing months ending December, divided by (maximum NCP kW for those months × days in the billing periods × 24) (Oncor Tariff for Retail Delivery Service, Sheet 1.3). Oncor uses this only on its Secondary > 10 kW schedule. The result applies for the following 12 billing months, and a premises with less than 90 days of history is assumed to be above 25%. TNMP uses the same formula, but only for Secondary > 5 kW service (TNMP Tariff, §6.1.1.1.3). AEP Texas's rate schedules don't use an annual load-factor test (AEP Texas Tariff, §§6.1.1.1.3–6.1.1.1.4).

Worked example

Illustrative. A site's 30-day bill shows 216,000 kWh and a metered peak demand of 500 kW.

Now say the site staggers two large motor starts and trims its peak to 400 kW, using the same energy:

The site used no less energy, but its load factor improved because the peak came down.

Why load factor drives all-in cost per kWh

On demand-billed service, part of your delivery cost is charged per kW of peak, not per kWh. When you divide those demand dollars by the energy you actually used, a lower load factor means each kWh carries more of the demand cost.

Spread over energy, for one monthly bill:

Demand charges per kWh = demand rate ($/kW-month) × peak kW ÷ kWh = demand rate ÷ (load factor × hours)

This works for one billing period only. TDSPs bill demand once per billing cycle, so the demand charge is not prorated by the number of days. Our calculator shows this figure only for a single billing period of 25 to 35 days. Use a $/kW rate with a kW peak, or a $/kVA rate with a kVA peak. Don't mix them.

Load factor calculator

Illustrative calculation for general information. Not a quote, offer, or estimate of savings. Uses only the figures you enter; actual bills include energy, delivery, and other charges.

If your bill shows demand in kVA, convert to kW first (kW = kVA x power factor) for load factor.

Enter energy used, peak demand and days to see the load factor.

Using an illustrative demand-based rate of $10.00 per kW-month over a 720-hour (30-day) billing period:

Load factorDemand charges per kWh = $10 ÷ (LF × 720)
25%$10 ÷ 180 = $0.0556
40%$10 ÷ 288 = $0.0347
60%$10 ÷ 432 = $0.0231
75%$10 ÷ 540 = $0.0185
95%$10 ÷ 684 = $0.0146

In the worked example, raising load factor from 60% to 75% cuts the demand portion from $5,000 (500 kW × $10) to $4,000 (400 kW × $10). Spread over 216,000 kWh, that is $0.0231 → $0.0185 per kWh. These are illustrative numbers. Real demand rates vary by TDSP, rate class, and voltage. Your billed demand can be higher than your metered peak because of a ratchet or a power-factor adjustment, and transmission (4CP) charges for larger customers are based on fixed annual values, not this month's peak. The Public Utility Commission of Texas is reviewing how ERCOT transmission costs are allocated, as required by Senate Bill 6 (Project No. 58000), and that method may change. See our demand charges and 4CP pages.

Load factor can also affect supply pricing. A flat, predictable load is generally simpler for a retail provider to serve than a peaky one, and suppliers may price load shape differently. How much that matters depends on the supplier and the product, so treat it as something to compare, not an assumption.

Load factor also matters under the rules. Oncor's tariff and a PUCT rule both use a 25% annual load factor threshold. Where a demand ratchet is used in a TDU's base rates, it must not apply to a nonresidential secondary-voltage customer with an annual load factor of 25% or less (16 TAC §25.244(c); Oncor Tariff, Sheet 1.3). That rule covers only nonresidential secondary-voltage service through one point of delivery and one meter, and only where the TDSP ratchets that class at all. Primary- and transmission-voltage customers don't get it. In Oncor's tariff it covers the base distribution charge on Secondary > 10 kW, and some riders are still billed on ratcheted demand. At TNMP it applies only to Secondary > 5 kW, where the same 25% test also decides which of two distribution rates applies; TNMP Primary and Primary-Substation keep the ratchet regardless of load factor (TNMP Tariff, §§6.1.1.1.3–6.1.1.1.5). CenterPoint and AEP Texas don't ratchet the secondary distribution charge at all, and their primary ratchets have no load-factor exemption (CenterPoint Tariff, Sheets 6.3–6.4; AEP Texas Tariff, §§6.1.1.1.3–6.1.1.1.4). See our demand charges page for each TDSP's ratchet.

What's typical?

Load factor depends on the building type and how it runs, so use any benchmark with caution. A peer-reviewed Oak Ridge National Laboratory study used 15-minute data from about 178,000 buildings in one U.S. utility territory. It found residential load factors of about 0.17, commercial load factors of 0.2–0.4 depending on year of construction, and 0.16–0.5 across building types (ORNL, "Nailing the peak," 2019). Offices, retail, and schools that run mostly in daytime and on weekdays tend to have low load factors. Their peaks come from cooling and occupancy for part of the day.

Continuous loads such as Bitcoin mining and many data centers work differently. EIA describes large flexible computing loads in ERCOT as modeled "constant throughout the day" in its forecasts (EIA, Oct. 2024). We have not found an authoritative public benchmark for miners' load factor, so we don't quote one. The math shows why it tends to be high. Illustrative: a 10 MW site that runs at full load except for curtailing completely 5% of the hours in a month uses 10 MW × 0.95 × 720 h = 6,840 MWh against a 10 MW peak. Its load factor is 6,840 ÷ (10 × 720) = 95%. That is separate from EIA's estimate that ERCOT large flexible loads have historically consumed about 65% of their approved capacity (EIA). That figure compares energy with approved interconnection capacity, not with the site's actual metered peak.

How to improve load factor

Load factor goes up when the peak comes down or when energy rises without a new peak. Only the first reliably lowers a bill.

  1. Find what sets the peak. Use interval data to identify the interval, the day, and the equipment involved.
  2. Stagger and sequence. Spread motor, chiller, and compressor starts. Bring load back in stages after outages and shutdowns.
  3. Cap demand with controls. Shed or defer non-critical loads, like water heating, EV charging, or batch processes, as a 15-minute interval nears a set limit.
  4. Shift flexible work off your own peak. Pre-cool, pre-heat, or move batch jobs to hours when the site is otherwise lightly loaded.
  5. Right-size and maintain equipment. Oversized or poorly controlled equipment can raise peaks without adding useful output.
  6. Don't add load just to raise the ratio. Using more energy to improve load factor usually raises the total bill.

How Kyber helps

Kyber is a PUCT-registered electricity broker. We can calculate your load factor from your bills or interval data, show how it affects your all-in cost per kWh under your current delivery tariff, and include your load shape when comparing supply offers. What any change saves depends on your tariff, your contract, and the market. We'll show the math behind any estimate.

What this page is not

This page is for general information. It is not a quote, an offer, or a commitment to transact, and it is not a substitute for a signed client agreement.

Sources

All accessed 15 November 2026.

  1. U.S. EIA, Glossary, "L" (Load factor): https://www.eia.gov/tools/glossary/index.php?id=L
  2. Oncor, Tariff for Retail Delivery Service, §6.1.1.1.3, Sheet 1.3 (eff. June 1, 2026), Determination of Annual Load Factor and Billing kW (pp. 72–74): https://www.oncor.com/content/dam/oncorwww/documents/about-us/regulatory/tariff-and-rate-schedules/Tariff%20for%20Retail%20Delivery%20Service.pdf
  3. PUCT, 16 Tex. Admin. Code §25.244, Billing Demand for Certain Utility Customers: https://ftp.puc.texas.gov/public/puct-info/agency/rulesnlaws/subrules/electric/25.244/25.244.pdf
  4. New, J. R., et al., "Nailing the peak: City-scale, building-specific load factor and contribution to a utility's hour of critical generation," Building Simulation 2019 (Oak Ridge National Laboratory): https://impact.ornl.gov/en/publications/nailing-the-peak-city-scale-building-specific-load-factor-and-con/
  5. U.S. EIA, "Data centers and cryptocurrency mining in Texas drive strong power demand growth," Today in Energy, Oct. 3, 2024: https://www.eia.gov/TODAYINENERGY/detail.php?id=63344
  6. CenterPoint Energy Houston Electric, Tariff for Retail Delivery Service (file dated Nov. 9, 2026), Ch. 1 Definitions, Sheet 1.1 (demand in kW or kVA; load factor); §§6.1.1.1.3–6.1.1.1.5, Sheets 6.3–6.5: https://assets.centerpointenergy.com/api/public/content/houston-electric-tariff-for-retail-delivery-service.pdf
  7. Texas-New Mexico Power (TNMP), Tariff for Retail Delivery Service (Docket 58964 book; rate schedules eff. Sept. 13, 2026), §6.1.1.1.3, "Determination of Annual Load Factor" (p. 98); §§6.1.1.1.4–6.1.1.1.5 (pp. 99–104): https://tnmp.com/sites/default/files/inline-images/TNMP%20Retail%20Tariff%20%2858964%29.pdf
  8. AEP Texas, Tariff for Retail Delivery Service (book eff. Nov. 6, 2026), Ch. 1 Definitions ("Load Factor"); §§6.1.1.1.3–6.1.1.1.4 (pp. 119–124): https://www.aeptexas.com/lib/docs/ratesandtariffs/Texas/AEP_TEXAS_TARIFF_Eff_Nov_6-2026-TC3.pdf

All rates and dollar amounts on this page are illustrative and are not TDSP tariff rates.

Prices shown are recent or historical ERCOT market data, which may be delayed, and are for information only. They are not a quote, offer, or forecast, and Holocron Kyber does not guarantee any price or savings. Actual costs depend on market conditions, your load, and the terms of your supply contract.